Hello All,
Is it obligatory to process power on sequence when NRF7002 is connected (IOVDD) permanently to Host's power supply e.g. 3,3V
Is it possible, do not make the power up sequence?
Is there any risk to put the module into the undefined state?
The power up sequence and requirements are:
- Supply VBAT/BUCKVBAT/BUCKVBATS/AFEVBAT
- Wait ≥ 6 ms
- Assert BUCKEN
- Wait ≥ 1 ms
- Supply IOVDD
The power down sequence and requirements are:
De-assert BUCKEN and power down IOVDD
- Power down VBAT
There are no specifics timing delay requirements as long as the sequence is correct.
Thank you